MAVİ HES VE REGÜLATÖRÜ
Our company’s business basis and also owner of Mavi Weir and HEPP final project works began in 2009 by Pro-sem Engineering Architecture Consultancy. %80 percentage of the project works has been completed until now.
Mavi Weir and HEPP Project’s water usage agreement, license, EIA (Environmental Impact Assesment) not necessary document, project approvals and all the necessary legal permits has been completed in 2010.
Project site will be completed by construction subcontractor Sim International Building Mine Industry and Foreign Trade Public Company in first quarter of 2012.
The electromechanical equipment of the Mavi HEPP, will be supplied by European’s leading manufacturers Andritz and Indar. The contracts has been signed and the erection of the equipment will begin on the first quarter of 2012.
Because the HEPP projects are the renewable energy projects , they limit the carbon release. For this reason they have given permission to do carbon trade. Cese Electric has signed a contract with Su-En Limited Company and the certificates will be gathered in 2012 February or March.